Utility Scale Solar + 400 kV EHV Grid272 MWp
Torre Bela Solar Park
Client / DeveloperNEOEN (Empreiteiro EPC: ACISA)
LocationAzambuja, Portugal
Timeline2023 - 2026
Project Overview
With 272 MWp installed capacity, the Torre Bela Solar Park is one of Portugal’s largest clean energy developments. HexaWatt provides comprehensive on-site supervision and QA/QC oversight covering ~500,000 tracker modules, 1,315 Huawei inverters and a 400 kV extra-high voltage transmission line.
Technical Specifications
Installed Capacity272 MWp
Solar Modules~500.000 unidades (Astroenergy, Chint, Risen)
Inverters1.315 x Huawei 215 kWp
Transformer Stations1 Smart Station 3 MW + 40 x 6 MW
Grid ConnectionLinha de Muito Alta Tensão 400 kV
Solar TrackersNextracker Horizon
Services Rendered:

1 / 6
Need similar engineering support?
We provide site supervision, owner’s engineering and commissioning for renewable power plants.
Contact Project TeamWhatsApp (+351 962 467 877)